Under Floor Heating System for Solid Floors
Polyplumb floor heating in solid or screeded floors incorporates the unique
Polyplumb screeded floor panel. The light weight plastic floor panels nest for easy
storage and carrying.
The floor panels are simply cut to the room shape.
They form a simple grid for the quickest possible pipe
laying and form a precise guide for minimum bending
radius. They set the pipe at exact centres and hold the
pipe against movement when screeding. The floor
panel holds the pipe above the insulation allowing full
screed surround. Optimum screed depth is 65mm
from panel base, i.e. 40mm from the pipe top.
Insulation below and at the edges of the floor screed is
required by Building Regulations. Edge insulation also
acts as an expansion joint.
| Key Design and Installation Information |
| Maximum heat output |
Approx. 100w/m2 (see output table) |
| Recommended design flow temperatures |
50° (see output table) |
| Maximum circuit length |
100m (15mm pipe) 120m (18mm pipe) |
| Maximum coverage per circuit |
11·1m2 at 300mm centres
21·2m2 at 200mm centres
30m2 at 300mm centres (18mm pipe) |
| Material Requirements (approx) |
| Pipe |
8·2 m/m2 at 100mm centres
4·5m/m2 at 200mm centres
3·3m/m2 at 300mm spacing (18mm
pipe only) |
| Floor plate usage |
1 plate/m2 allowing for cutting
(Actual 1·2m2/plate) |
| Edging insulation |
1·1m/m2 |
| Conduit pipe |
2m/circuit |
Note : Rooms packs are supplied with pipe at 100mm centres (100m coils) and House Packs with pipe at 200mm centres (80m coils).

Solid Floor Installation Diagram
Pre-installation requirements
The sub floor must be swept clean and be free from
mortar residues.
Insulation
Insulation should be laid in accordance with the
requirements of Building Regulations.
Edge insulation strips
Edge insulation strips permit the free expansion of
the floor screed and need to be installed around all surrounding walls and fixed constructions, such as
columns, steps and access doorways. (installation
pictured top middle).
The edge insulation must also be used to separate
areas where either the total area exceeds 40m2 or
lengths less than 8m exceed a length x width ratio of
1:2.5, eg corridors. Edge insulation is bent at 90º near
to the base, to form a double-sided self-adhesive strip,
which bonds the floor plates to the floor insulation.
Edge insulation is laid in addition to perimeter
insulation required by Building Regulations.

Floor panels
The floor panels are laid above pre-installed insulation
and are overlapped at the edges.
Note that the 1/2 castellation overlaps the 3/4
castellation; the first panel is therefore laid with the 1/2
castellation edge nearest to the wall. The panel can
either be cut using a saw or snips, or simply
overlapped to the nearest fit. The floor panel should not be used at the base of the manifold, as pipes need
to be closer together than the floor panels permit.
Pipes around this area should be retained by pipe
clips, which may also be used intermittently to secure
the clip plate to the insulation.
Pipe
When the floor to be heated is covered by floor panels,
pipe can be installed at the pre-designed centres.
Unwrap the pipe from the coil completely and take
pipe from the outside of the coil by unrolling the pipe
in the direction that the pipe is being laid.
Pipe laying
The floor panel ensures that pipe is laid at the
pre-determined spacing. 15mm pipe is laid at 100mm
or 200mm centres as required; 18mm pipe may also be
laid at 300mm centres.
The minimum bend radius is ensured by encircling two
castellations for a 90° bend or three castellations for a
180° bend (see diagram below).

Pipe laying - Step one
All circuits to be laid at 100mm and 200mm centres
must be laid in a spiral configuration. The first loop of
pipe should be laid around the perimeter of the area to
be covered by that circuit. The next loop should be laid
either 200mm from this pipe for spacing of 100mm, or
400mm from this pipe for spacing of 200mm.

Pipe laying - Step two
Continue the loop of the pipe to the centre of the
panels, leaving enough space to form a double return
(“s” shape in the centre of the loop).

Pipe laying - Step three
Continue working out from the centre by filling the
space between the two pipes on the primary circuit,
therefore leaving pipes at the required spacing centres.

Where 300mm spacing is required (18mm pipe
systems only) a meander pattern can be used. The pipe
simply crosses the room from one side to the other
encapsulating three castellations at each return bend.

Conduit pipe
Conduit pipe should be
used around heating pipe
where the pipe passes
through edge insulation
strips, ie room, or through
expansion joints within
the floor. A section of
conduit 400mm long
should be applied.
Conduit is also used where the pipe leaves the floor
adjacent to the manifold. This is normally threaded
down the pipe after the pipework has been installed.
Screed cover
Screed should only be laid over the pipe that is
pressurised to 6 bar, as this prevents pipes being
crushed during the screeding process. Sand and
cement screed should be laid to a depth of 65mm
minimum (40mm cover over pipe minimum).
Screed significantly greater than this thickness will delay initial heating times.
Timber - suitable for Polyplumb solid floor
and suspended floor systems
Although many people are concerned the effect of heat
on a timber floor, much of this concern is misplaced.
Of more importance is the floor moisture content.
Timber floors should be laid at moisture content of
10% to 11%, which during the heating season will
reduce to 8% to 9% and cause a very small amount
of shrinkage.
The floor will re-absorb some moisture when the
heating is not operating and the moisture content will
increase to 12% to 13%
Application of Timber floors
over Solid floor systems
Where traditional oak flooring is to be laid on a solid
floor, joists can be used at 1 metre spacings to provide
a fixing point for the boards.
Insulation, floor plate and pipe can then be laid
between the joists and screed laid level with the top of
the joists (see diagram).
Individual circuits of pipe are laid between each set of
joists and care should be taken to ensure that the
screed is completely dry prior to the wood board
covering being laid (see diagram). |