Underfloor Heating Commissioning Procedure
Once installed, Polyplumb floor heating systems should be tested thoroughly to
ensure they are working effectively, including initial filling of the system and system
balancing.
Initial filling of system:
1. Close manifold isolating valves.
2. Connect a hose pipe to the manifold flow port via
the drain off/filling point on the manifold. The other
end of the hose should be connected to a mains
cold water supply.
3. Connect a second hose to the return manifold and
take it to a suitable discharge point such a drain or
back inlet gully.
4. Open one of the blue decorator’s caps on top of the
manifold and commence filling the system via the
mains cold water supply. Once the water is running
smoothly through the circuit and all of the air has
been expelled, open the second blue cap and close
the first. Repeat this process until all of the circuits
have been filled and the system is free of air.
Close the drain / filling points and remove the hoses.
5. Connect a suitable pressure test pump to the flow
manifold filling point and test the system to 6 Bar.
Leave system under pressure for one hour to
confirm the integrity of the installation. Once the
pressure test is complete reduce the system
pressure down to 3 Bar whilst the screed is applied.
Important note: Do not leave system under pressure
during cold weather when there is a risk of freezing.
System balancing:
Once the system is up and running it will be necessary
to balance the system in accordance with the design
data as provided. This should be done using the
following method.
1. Open the manifold isolating valves. Ensure that the
boiler is operating correctly and that the correct
temperature water is being provided at the manifold
mixing valve. Please note that due to the design of
the mixing valve it is necessary to provide water
from the boiler at least 15ºC hotter that the required
underfloor heating operating temperature.
For example; if the underfloor heating system has
been designed to operate at a flow temperature of
50ºC, the boiler should be able to provide a primary
flow temperature to the manifold mixing valve of
65ºC min. (Please note that for systems connected
to a heat pump installation different criteria may
apply. Please contact Polypipe Technical Support for
further information.) Adjust the mixing valve
temperature setting accordingly to match the precise
manifold design requirement using the dial
thermometers as supplied.
2. Ensure that the underfloor heating circulating pump
is set to a suitable fixed head speed using the pump
adjustment facility. This is particularly important for
systems fitted with modulating pumps. Remove the
blue caps from the manifold return rail (or actuators
if already fitted) and using the radiator key supplied
adjust the circuit/s to each room in accordance with
the Polypipe design data. This is done by fitting the
radiator key over the square fitting that protrudes
from the top of the valve body. By turning the key
clockwise the flow rate is decreased. To increase
flow rate turn the key anticlockwise. Adjust each
circuit until the flow meter on the manifold flow rail
reads the required flow rate. Repeat the procedure
for all circuits connected to the manifold. If a
modulating pump is fitted return the pump to its
modulating operation mode.
3. Refit the manifold actuators and check their correct
operation to each circuit by operating the
appropriate room thermostats.
Pressure testing in sub zero temperatures
Special precautions are necessary if the pressure
testing is to take place in sub-zero temperatures.
This applies particularly when using the screeded floor
heating system, where most of the pipe is encased in
screed. Due to the contact between pipe and floor
panel on screeded installations, where the screed does
not completely surround the pipe, there may be points
where strain is created on the pipe in freezing
conditions, which is not normally present. Therefore, it
is advisable to drain the floor heating system once
testing and screeding has been completed.
System chlorination
Short term chlorination for disinfection of supply
pipework and normal levels of chlorine in UK domestic
water supplies will not have an adverse effect on
Polyplumb. Polyplumb is not suitable, however, for
systems that carry a high concentration of chlorine, ie
supplies to swimming pools, etc.
Tips:
If there is an excessive amount of air present the
system will be noisy and the flow meters may
appear to bounce up and down. If this happens,
repeat the initial filling procedure until the system
is fully purged of air.
If the system has been left standing for a long
period of time or if contaminants are present in
the system water, the flow meters may appear
discoloured or cease to work. If this is the case,
turn off the manifold isolating valves and remove
the manifold flow meter/s. Using a soft brush,
gently wash under a tap until all of the debris has
been removed. Check the manifold opening for
any signs of contamination and flush the system
if necessary. Refit manifold flow meters.
Should the damage to the flow meter/s be too
great it/they should be replaced.
If the original system design data has been lost or
is unavailable it is possible to adjust the manifold
flow rates using the simple rule of thumb method
as described below:
As the maximum length of any single Polypipe
underfloor heating circuit should not exceed
100m, we know that when installed in to a solid
floor system using 100mm pipe spacings and
allowing for minimum connection lengths, it is
possible to cover approximately 10m2 of floor
area. Given the maximum heat output achieveable
from this type of system (100 watts per m2) we
therefore know that a 10m2 area of floor can give
out approximately 1kW of heat. In order to meet
this requirement a flow rate setting of
approximately 1.5 litres per minute will be
required.
Typical average flow rates assuming a 10ºC
temperature drop across the manifold:
- 50 watts per m2 = Flow rate setting 0.7 l/pm
- 75 watts per m2 = Flow rate setting 1.0 l/pm
- 100 watts per m2 = Flow rate setting 1.5 l/pm
|